WWTP Updates March 2011

Air release manholes and valves are in place and construction of the holding pond at the Lindsborg Golf Course is complete. Testing of the line has been conducted and a few tests on the pumps remain. Once the tests are done reclaimed water can be pumped to the new holding pond.

Air Release Manhole

March 3, 2011

Golf Course Pond

March 3, 2011

A two inch line was laid around the plant and connected to hydrants; reclaimed effluent water is then pumped through the line for basin wash down and filling and can be used for lawn irrigation as well.

Reclaimed Effulent Water Line

March 10, 2011